KIIFB PROJECT 2016-17 Improvements to Muttungal - Nadapuram -Pakramthalam Road between km 0/000 to 11/855 In Kozhikode Dist.

   General Details
Roads
Vatakara Section
Roads
R & B North Circle
Roads Division Kozhikkode
Roads Sub Division Vadakara
Vatakara Section
KOZHIKODE
   Project Details
2016-17
KIIFB
Other KIIFB Works
RD/2016/3905
415,000,000/-
(Forty One crore Fifty lakh )
G.O.(Rt)No.1192/2016/PWD 20-08-2016 300,000,000/-
(Thirty crore )
4846/2017-2018 18-11-2017 415,000,000/-
(Forty One crore Fifty lakh )
   Tender Details
PMU-KRFB/T-18/2017-18 25-11-2017 350,021,760/-
(Thirty Five crore Twenty One thousand Seven hundred Sixty )
ULCCS Ltd
   Agreement Details
15/PWD004-26/PD/PMU-KRFB/2017-18 15-02-2018 350,021,760/-
(Thirty Five crore Twenty One thousand Seven hundred Sixty )
22-02-2018 18 Months 22-08-2019 30-11-2020
   Work Progress (Last Updated On :29-01-2021 11:10:00 AM)
Work in progress
86%
Drain completed for a total length of 17397m\r\nRetaining wall completed for a total length of 281.73m\r\nNo of culvert completed 20\r\nGSB completed for a total length of 8536m\r\nWMM completed for a total length of 9863m\r\nDBM completed for a total length of 10038.3m\r\nBC completed for a total length of 2000m
112,462,183/-
(Eleven crore Twenty Four lakh Sixty Two thousand One hundred Eighty Three )
32%
0/-
View Progress Photo Gallery