NABARD RIDF XXIV Construction Of KannittakadavuIllichira Road in Ambalappuzha LAC
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Roads Section Ambalappuzha | |||||
| Roads | |||||
| R & B South Circle | |||||
| Roads Division Alappuzha | |||||
| Roads Sub Division Alappuzha | |||||
| Roads Section Ambalappuzha | |||||
| ALAPPUZHA | |||||
| Project Details | |||||
| 2019-20 | |||||
| 5054-04-337-94-00-16-0-P-V | |||||
| NABARD Works | |||||
| RIDF XXIV | |||||
| RD/2018/11944 | |||||
| 99,200,000/- (Nine crore Ninety Two lakh )
|
|||||
| G.O.(Rt)No.202/2019/PWD | 11-02-2019 | 99,200,000/- (Nine crore Ninety Two lakh )
|
| ORDER No.RdDnALP/2019-2020/RD/2018/11944 | 08-07-2019 | 99,200,000/- (Nine crore Ninety Two lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 12/SESC | 21-11-2019 | 93,708,471/- (Nine crore Thirty Seven lakh Eight thousand Four hundred Seventy One )
|
M P Jolly | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 98/SESC/2019-20 | 07-01-2020 | 93,708,471/- (Nine crore Thirty Seven lakh Eight thousand Four hundred Seventy One )
|
07-01-2020 | 9 Months | 07-10-2020 | 31-03-2021 |
| Work Progress (Last Updated On :24-06-2021 11:11:19 AM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| Work completed | |||||
| 47,230,496/- (Four crore Seventy Two lakh Thirty thousand Four hundred Ninety Six )
50%
|
|||||
| 51,969,504/- (Five crore Nineteen lakh Sixty Nine thousand Five hundred Four )
|
|||||
| View Progress Photo Gallery | |||||