KIIFB-2016-17-Stimulus package-Improvements and providing DBM&BC to Kankol-Cheemeni road km 0/000 to 10/135 in Kannur District
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Payyannur Section | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Kannur | |||||
| Roads Sub Division Taliparamba | |||||
| Payyannur Section | |||||
| KANNUR | |||||
| Project Details | |||||
| 2016-17 | |||||
| KIIFB | |||||
| A | |||||
| 2016/3989 | |||||
| 202,500,000/- (Twenty crore Twenty Five lakh )
|
|||||
| G.O (Rt) NO.1192/2016/PWD DATED | 20-08-2015 | 100,000,000/- (Ten crore )
|
| 707/2018-2019,Dated 17.05.2018 | 17-05-2018 | 202,500,000/- (Twenty crore Twenty Five lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| pmukrfb/T17/2018-19 | 30-06-2018 | 208,927,592/- (Twenty crore Eighty Nine lakh Twenty Seven thousand Five hundred Ninety Two )
|
K V Joseph | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| No.48/PWD004-96/PD/PMU-KRFB/2018-19 | 24-10-2018 | 208,927,592/- (Twenty crore Eighty Nine lakh Twenty Seven thousand Five hundred Ninety Two )
|
30-10-2018 | 18 Months | 29-04-2020 | 00-00-0000 |
| Work Progress (Last Updated On :23-02-2021 2:23:49 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| Work completed | |||||
| 199,785,954/- (Nineteen crore Ninety Seven lakh Eighty Five thousand Nine hundred Fifty Four )
96%
|
|||||
| 8,153,107/- (Eighty One lakh Fifty Three thousand One hundred Seven )
|
|||||
| View Progress Photo Gallery | |||||