KIIFB Improvemens includingDBM & BC to Ulikkal -Thermala-Kanhileri-Kaniyarvayal road between KM 0/00 to 18/00

   General Details
Roads
Irikkur Section
Roads
R & B North Circle
Roads Division Kannur
Roads Sub Division Taliparamba
Irikkur Section
KANNUR
   Project Details
2016-17
KIIFB
Other KIIFB Works
2016/4515
612,700,000/-
(Sixty One crore Twenty Seven lakh )
GO(RT) NO.1502/2016/PWD 01-11-2015 612,700,000/-
(Sixty One crore Twenty Seven lakh )
1719/2018-19 06-07-2019 612,700,000/-
(Sixty One crore Twenty Seven lakh )
   Tender Details
003 11-09-2018 543,284,740/-
(Fifty Four crore Thirty Two lakh Eighty Four thousand Seven hundred Forty )
Eranad Engineering enterprises
   Agreement Details
"No.52/PWD006-13/PD/PMU-KRFB/2018-19 30-10-2018 543,284,740/-
(Fifty Four crore Thirty Two lakh Eighty Four thousand Seven hundred Forty )
07-11-2018 24 Months 06-06-2020 12-04-2021
   Work Progress (Last Updated On :23-02-2021 2:20:58 PM)
Work in progress
67%
54 culverts completed.11300m drain works completed.6400m DR masonry completed.2250m CC wall completed.GSB 6570 M completed.WMM 4390m completed.DBM 3000m completed
102,872,750/-
(Ten crore Twenty Eight lakh Seventy Two thousand Seven hundred Fifty )
19%
0/-
View Progress Photo Gallery