KIIFB Improvemens includingDBM & BC to Ulikkal -Thermala-Kanhileri-Kaniyarvayal road between KM 0/00 to 18/00
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Irikkur Section | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Kannur | |||||
| Roads Sub Division Taliparamba | |||||
| Irikkur Section | |||||
| KANNUR | |||||
| Project Details | |||||
| 2016-17 | |||||
| KIIFB | |||||
| Other KIIFB Works | |||||
| 2016/4515 | |||||
| 612,700,000/- (Sixty One crore Twenty Seven lakh )
|
|||||
| GO(RT) NO.1502/2016/PWD | 01-11-2015 | 612,700,000/- (Sixty One crore Twenty Seven lakh )
|
| 1719/2018-19 | 06-07-2019 | 612,700,000/- (Sixty One crore Twenty Seven lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 003 | 11-09-2018 | 543,284,740/- (Fifty Four crore Thirty Two lakh Eighty Four thousand Seven hundred Forty )
|
Eranad Engineering enterprises | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| "No.52/PWD006-13/PD/PMU-KRFB/2018-19 | 30-10-2018 | 543,284,740/- (Fifty Four crore Thirty Two lakh Eighty Four thousand Seven hundred Forty )
|
07-11-2018 | 24 Months | 06-06-2020 | 12-04-2021 |
| Work Progress (Last Updated On :23-02-2021 2:20:58 PM) | |||||
|---|---|---|---|---|---|
| Work in progress | |||||
|
67%
|
|||||
| 54 culverts completed.11300m drain works completed.6400m DR masonry completed.2250m CC wall completed.GSB 6570 M completed.WMM 4390m completed.DBM 3000m completed | |||||
| 102,872,750/- (Ten crore Twenty Eight lakh Seventy Two thousand Seven hundred Fifty )
19%
|
|||||
| 0/- | |||||
| View Progress Photo Gallery | |||||