Improvements to providing BM&BC to Chandapura-Pariyaram Medical College-Sreestha -Neruvembram-Ezhome - Kottakeel - Kavinmunambu - Parappool-Vellikkeel road junction- Vellikkeel - Ozhakrome - Kannapuram road Km. 0/000 to 29/771PRICE ID 2017/4046)
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Roads Sub Division Kannur | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Kannur | |||||
| Roads Sub Division Kannur | |||||
| KANNUR | |||||
| Project Details | |||||
| 2016-17 | |||||
| KIIFB | |||||
| Other KIIFB Works | |||||
| RD/2017/4046 | |||||
| 386,500,000/- (Thirty Eight crore Sixty Five lakh )
|
|||||
| APR-3/337/2017/KIIFB DTD-01-01-2018 | 01-01-2016 | 388,900,000/- (Thirty Eight crore Eighty Nine lakh )
|
| 6399/2017-18 | 15-03-2018 | 386,500,000/- (Thirty Eight crore Sixty Five lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 0000000 | 00-00-0000 | 359,023,943/- (Thirty Five crore Ninety lakh Twenty Three thousand Nine hundred Forty Three )
|
KK Builders civil engineering contractors Peravoor | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 63/PWD0004-89/PD/PMU-KRFB/2018-19 | 27-11-2018 | 359,023,943/- (Thirty Five crore Ninety lakh Twenty Three thousand Nine hundred Forty Three )
|
04-12-2018 | 24 Months | 04-12-2020 | 30-06-2021 |
| Work Progress (Last Updated On :23-02-2021 2:15:11 PM) | |||||
|---|---|---|---|---|---|
| Work in progress | |||||
|
65%
|
|||||
| 4 Extension Culvert completed, 5404.85 m Drainage and 1000.00 side protection work completed.2786.00 DR Retaining wall completed. Culvert, Drainage and side protection work in progress.12.130 km DBM completed. 14.00 km to be completed.Kavin munampu - Parappool road Ozhakrome - Kannapuram road GSB and WMM work in progress | |||||
| 107,010,212/- (Ten crore Seventy lakh Ten thousand Two hundred Twelve )
30%
|
|||||
| 42,006,897/- (Four crore Twenty lakh Six thousand Eight hundred Ninety Seven )
|
|||||
| View Progress Photo Gallery | |||||