KIIFB - Improvements to Perambra - Cheruvannur - Vatakara road between Km. 0/000 to 9/800 in Kozhikode District.
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Perambra Section | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Kozhikkode | |||||
| Roads Sub Division Koyilandy | |||||
| Perambra Section | |||||
| KOZHIKODE | |||||
| Project Details | |||||
| 2017-18 | |||||
| KIIFB | |||||
| Other KIIFB Works | |||||
| RD/2017/2673 | |||||
| 244,000,000/- (Twenty Four crore Forty lakh )
|
|||||
| 31/KIIFB/2016 | 19-09-2017 | 244,000,000/- (Twenty Four crore Forty lakh )
|
| 1991/2017-2018 | 19-09-2017 | 244,000,000/- (Twenty Four crore Forty lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| PMU-KRFB/T-02/2017-18 | 26-09-2017 | 193,859,634/- (Nineteen crore Thirty Eight lakh Fifty Nine thousand Six hundred Thirty Four )
|
BAAB Construction Pvt Ltd | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 4/PWD-004-07/PD/PMU-KRFB/2017-18 | 05-12-2017 | 193,859,634/- (Nineteen crore Thirty Eight lakh Fifty Nine thousand Six hundred Thirty Four )
|
16-01-2018 | 12 Months | 15-01-2020 | 30-07-2020 |
| Work Progress (Last Updated On :29-07-2020 9:37:34 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| Nearing completion, small rectification works for interlock, drain, Irish drain etc have to be done. | |||||
| 95,449,583/- (Nine crore Fifty Four lakh Forty Nine thousand Five hundred Eighty Three )
49%
|
|||||
| 46,985,332/- (Four crore Sixty Nine lakh Eighty Five thousand Three hundred Thirty Two )
|
|||||
| View Progress Photo Gallery | |||||