Go back

NABARD RIDF - XX III 2018-19 Improvements and Providing BM & BC to Chunakkara Laha Road (Chettikulangara - chunakkara Road) Km 3/000 to 12/000)

   General Details
Roads
Roads Section Kattanam
Roads
R & B South Circle
Roads Division Alappuzha
Roads Sub Division Mavelikkara
Roads Section Kattanam
ALAPPUZHA
   Project Details
2018-19
NABARD Works
RIDF XXIII
RD/2016/10682
60,000,000/-
(Six crore )
GO (Rt) No1777/2018/ PWD 15-11-2018 60,000,000/-
(Six crore )
ORDER No.KTNMSn/2018-2019/2017/10682 28-01-2019 60,000,000/-
(Six crore )
   Tender Details
00-00-0000 0/-
   Agreement Details
34/SESC/2019-20 25-07-2019 55,955,180/-
(Five crore Fifty Nine lakh Fifty Five thousand One hundred Eighty )
02-08-2019 9 Months 02-05-2020 28-02-2021
   Work Progress (Last Updated On :29-07-2021 4:52:08 PM)
Work in progress
99%
Drainage work in progress.BC work completed.Safety work in progress
43,894,000/-
(Four crore Thirty Eight lakh Ninety Four thousand )
78%
15,927,045/-
(One crore Fifty Nine lakh Twenty Seven thousand Forty Five )
View Progress Photo Gallery