FDW 2018-19 PROVIDING BM &BC TO KARIKODU VELLIYAMATTOM ROAD Km. 6/200 TO 12/200
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Roads Sub Division Thodupuzha | |||||
| Roads | |||||
| R & B Central Circle | |||||
| Roads Division Idukki | |||||
| Roads Sub Division Thodupuzha | |||||
| IDUKKI | |||||
| Project Details | |||||
| 2018-19 | |||||
| 3054-03-337-96-00-00-0-N-V | |||||
| Non Plan | |||||
| Flood Damage Works | |||||
| RD/2019/1269 | |||||
| 53,794,405/- (Five crore Thirty Seven lakh Ninety Four thousand Four hundred Five )
|
|||||
| G.O(Rt) No. 189/2019/PWD | 05-02-2019 | 54,500,000/- (Five crore Forty Five lakh )
|
| 9068/2018-19 | 18-02-2019 | 54,500,000/- (Five crore Forty Five lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| PQ27/SECCA/2018-19 | 08-03-2019 | 58,965,171/- (Five crore Eighty Nine lakh Sixty Five thousand One hundred Seventy One )
|
Raji Mathew, Pamplaniyil Houde, Bharananganam | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 69/SECCA/2019-20 | 16-09-2019 | 58,965,171/- (Five crore Eighty Nine lakh Sixty Five thousand One hundred Seventy One )
|
25-09-2019 | 12 Months | 25-09-2020 | 31-12-2020 |
| Work Progress (Last Updated On :25-06-2021 0:27:25 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| 58,246,438/- (Five crore Eighty Two lakh Forty Six thousand Four hundred Thirty Eight )
99%
|
|||||
| 0/- | |||||