NABARD RIDF XXIV- Improvements to Mananthavady - Ambukuthi - Jessi- Pilakkavu- Pancharakolly road (ODR) from km 0/000 to 5/000 in Mananthavady LAC
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Roads Division Wayanad | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Wayanad | |||||
| WAYANAD | |||||
| Project Details | |||||
| 2018-19 | |||||
| 5054-04-337-94-00-16-0-P-V | |||||
| NABARD Works | |||||
| RIDF XXIV | |||||
| RD/2018/11853 | |||||
| 70,000,000/- (Seven crore )
|
|||||
| GO (Rt) No. 202/2019/PWD | 11-02-2019 | 70,000,000/- (Seven crore )
|
| 9773/2018-2019 | 10-03-2019 | 70,000,000/- (Seven crore )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 2019_PWD_280757_1 | 15-11-2019 | 69,305,674/- (Six crore Ninety Three lakh Five thousand Six hundred Seventy Four )
|
Benoy T V, PWD Contractor, Thandekattu House, Mailambadi P O, Wayanad 673 591 | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| SE(K) 158/2019-20 | 15-11-2019 | 67,996,404/- (Six crore Seventy Nine lakh Ninety Six thousand Four hundred Four )
|
23-11-2019 | 9 Months | 22-08-2020 | 00-00-0000 |
| Work Progress (Last Updated On :16-12-2020 4:05:21 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| 8 culverts, CC drain and Retaining wall construction completed. BM and BC works and Road Safety works completed. | |||||
| 26,750,053/- (Two crore Sixty Seven lakh Fifty thousand Fifty Three )
39%
|
|||||
| 33,732,805/- (Three crore Thirty Seven lakh Thirty Two thousand Eight hundred Five )
|
|||||