Go back
Providing BM & BC to Vengapally Anoth Pozhuthana road ch between 0/000 to 4/800 in Wayanad District
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Roads Division Wayanad | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Wayanad | |||||
| WAYANAD | |||||
| Project Details | |||||
| 2018-19 | |||||
| Non Plan | |||||
| Flood Damage Works | |||||
| RD/2017/4200 | |||||
| 50,000,000/- (Five crore )
|
|||||
| GO(Rt) No. 1978/PWD/2018 | 22-12-2018 | 50,000,000/- (Five crore )
|
| 8683/2018-19 | 10-02-2019 | 50,000,000/- (Five crore )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| . | 00-00-0000 | 253,215,015/- (Twenty Five crore Thirty Two lakh Fifteen thousand Fifteen )
|
|||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| SE(K) 86/2019-20 | 13-08-2019 | 47,278,452/- (Four crore Seventy Two lakh Seventy Eight thousand Four hundred Fifty Two )
|
22-08-2019 | 6 Months | 22-02-2020 | 31-12-2020 |
| Work Progress (Last Updated On :18-06-2021 9:45:26 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| Work completed | |||||
| 16,189,472/- (One crore Sixty One lakh Eighty Nine thousand Four hundred Seventy Two )
34%
|
|||||
| 28,259,153/- (Two crore Eighty Two lakh Fifty Nine thousand One hundred Fifty Three )
|
|||||
| View Progress Photo Gallery | |||||