Go back
KASARAGOD DEVELOPMENT PACKAGE-PALLAM-MALANGARA-PAJJANE ROAD MUNDYARHADUKA-MUGU-PUTHOGE ROAD BM AND BC IN PUTHIGE G.P ,
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Roads Sub Division Kasaragod | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Kasaragod | |||||
| Roads Sub Division Kasaragod | |||||
| KASARGOD | |||||
| Project Details | |||||
| 2018-19 | |||||
| 000-00-000-00-00-00-00-N-V | |||||
| Deposit Works | |||||
| Other Deposit Works | |||||
| RD/2019/3958 | |||||
| 109,100,000/- (Ten crore Ninety One lakh )
|
|||||
| G.O.(Ms)No.16/2019/P&EA | 08-03-2019 | 109,100,000/- (Ten crore Ninety One lakh )
|
| 1678/2019-2020 | 20-08-2019 | 109,100,000/- (Ten crore Ninety One lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| PWD/PQ 2019-20/6480/Rddnksd | 18-12-2019 | 96,506,270/- (Nine crore Sixty Five lakh Six thousand Two hundred Seventy )
|
Sri.M.A.Ameer,PWD Contracor,Munambath(House)Chengala(PO)Ksaragod671541 | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| EE/KSD/14/2020-21 | 22-06-2020 | 72,491,020/- (Seven crore Twenty Four lakh Ninety One thousand Twenty )
|
01-07-2020 | 1 Years | 30-07-2021 | 00-00-0000 |
| Work Progress (Last Updated On :15-12-2020 4:44:58 PM) | |||||
|---|---|---|---|---|---|
| Work in progress | |||||
|
8%
|
|||||
| Earth work Escavation in progress,gradient cutting progresing, Side protection wall work under progress. | |||||
| 0/-
0%
|
|||||
| 72,491,020/- (Seven crore Twenty Four lakh Ninety One thousand Twenty )
|
|||||
| View Progress Photo Gallery | |||||