NABARD-RIDF-XXIV Improvement to Naduvannur-Koottalida Road between km 0/000 to 4/625 in Kozhikode District.
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Perambra Section | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Kozhikkode | |||||
| Roads Sub Division Koyilandy | |||||
| Perambra Section | |||||
| KOZHIKODE | |||||
| Project Details | |||||
| 2018-19 | |||||
| NABARD Works | |||||
| RIDF XXIV | |||||
| RD/2018/1867 | |||||
| 60,000,000/- (Six crore )
|
|||||
| GO(Rt) No: 1777/2018/PWD | 15-11-2018 | 60,000,000/- (Six crore )
|
| 8237/2018-19 | 31-01-2019 | 60,000,000/- (Six crore )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 2019_PWD_281815_1 | 13-08-2019 | 51,628,448/- (Five crore Sixteen lakh Twenty Eight thousand Four hundred Forty Eight )
|
Ahammed Haris B | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| SE(K)109/2019-20 | 06-09-2019 | 51,628,448/- (Five crore Sixteen lakh Twenty Eight thousand Four hundred Forty Eight )
|
14-10-2019 | 7 Months | 14-05-2020 | 28-02-2021 |
| Work Progress (Last Updated On :20-11-2020 0:27:14 PM) | |||||
|---|---|---|---|---|---|
| Work in progress | |||||
|
40%
|
|||||
| Culvert and Drainage work completed. WMM Work to be started. | |||||
| 2,773,644/- (Twenty Seven lakh Seventy Three thousand Six hundred Forty Four )
5%
|
|||||
| 48,854,804/- (Four crore Eighty Eight lakh Fifty Four thousand Eight hundred Four )
|
|||||
| View Progress Photo Gallery | |||||