| Sl.No | Project Name | Office | Admnistrative Sanction [Order No,Dated,Amt] |
Current Status of Work | Physcical Progress | Financial Progress | |||
|---|---|---|---|---|---|---|---|---|---|
| 51 | Annual Plan - Strengthening from KM 76 000 to KM 117 600 of NH 766 (Old NH 212) in Wayanad district |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION KOZHIKODE Sub Division:- NH SUB DIVISION KODUVALLY |
|
Work in progress Drain work side protection works in progress. DBM completed. BC work in progress . BC 15.5 km completed. |
70%
|
59%
|
|||
| 52 | Re Construction of Korappuzha Bridge in NH 66 at Elathur |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION KOZHIKODE Sub Division:- NH BYPASS SUB DIVISION KOZHIKODE |
|
Work in progress Bridge proper completed. Final finishing work an service road work in progress. Bridge inaugurated on 17/02/2021 |
95%
|
51%
|
|||
| 53 | Construction of a bridge across Chaliyar river at Elamaramkadavu connecting Malappuram & Kozhikode District in the State of Kerala |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION MALAPPURAM |
|
Work in progress 1 Abutment , 7 piers and 3 beams and slab of 1 span are completed |
48%
|
30%
|
|||
| 54 | Coastal highway Reach 1: Padinjarekkara to Unniyal junction (Km 0/000 - 15/000) |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION MALAPPURAM Sub Division:- NH SUB DIVISION KUTTIPURAM |
|
Work in progress Work in progress |
47%
|
40%
|
|||
| 55 | Improvements to Vandumthara Ittakadavu road in Palakkad District |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION MALAPPURAM |
|
Work in progress CD Work iis completed GSB & WMM work is completed . |
62%
|
0%
|
|||
| 56 | Improvements to Irattakulam Vaniyampara road in Palakkad District |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION MALAPPURAM |
|
Work in progress 95% work completed.BC work Almost completed Road Furnishing work started |
95%
|
78%
|
|||
| 57 | Widening to 2 lane with paved shoulders from km 87/000 to 133/720 ( Nattukal to Thanavu Jn. in Palakkad) of Nh 966 (Old NH213) in the State of Kerala on EPC mode |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION MALAPPURAM Sub Division:- NH SUB DIVISION PALAKKAD Section:- NH SECTION PALAKKAD |
|
Work in progress Site handed over on 23.08.2017. For Land Acquisition requisition for 3 A notification got druva and fresh 3A proposal was prepared and joint inspection was conducted with LA authorities for final 3D notification uploaded in Bhoomorasi Portal.CD work for entire strecth almost Completed..Bridge work at Thuppanaad,Klladikode,Kanjirapuzha,Ponnamcode,Eruvilthodu,chooriyodu is in progress..DBM work is completed for a length of 36.65km and BC for a length of 21.00km. |
55%
|
54%
|
|||
| 58 | CRF-2016-17- Improvements to Kuzhalmannam - Koduvayur road in Palakkad district in the state of Kerala |
Circle:- NH NORTH CIRCLE Division:- NH DIVISION MALAPPURAM |
|
Work in progress Work in progress |
90%
|
55%
|
|||
| 59 | CRF 2018 2019 Improvements to Kodassanadu padanilam Bharanikavu road in Alappuzha District |
Circle:- NH SOUTH CIRCLE Division:- NH DIVSION ALAPPUZHA |
|
Work in progress BC completed and road marking work in progress |
90%
|
0%
|
|||
| 60 | CRF 2018-2019 Imorovements to NH Evoor Jn Evoor temple Panachumudu Cheppad NH Muttam Karanjoor Muttam road in Alappuzha District |
Circle:- NH SOUTH CIRCLE Division:- NH DIVSION ALAPPUZHA |
|
Work in progress BC work started . Drain & interlock work of Evoor temple road completed |
85%
|
46%
|
|||