| Sl.No | Project Name | Office | Admnistrative Sanction [Order No,Dated,Amt] |
Current Status of Work | Physcical Progress | Financial Progress | |||
|---|---|---|---|---|---|---|---|---|---|
| 61 | KIIFB 2016-17 Construction of bridge across Mayiladi river at Malampuzha ring road |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Palakkad |
|
Work Stopped Work Handed over to KIIFB |
0%
|
0%
|
|||
| 62 | Construction of Panampalam Bridge across Tirur Puzha in Tanur LAC in Malappuram dist. |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad |
|
Work in progress Work Handed over to KIIFB on 11/08/2021 |
75%
|
20%
|
|||
| 63 | KIIFB Project 2016 17 TRAN 8 PWD 001 36 Construction Of Chullimadu Bridge across GayathriRiverin Alathur LAC in Palakkad District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad |
|
Work in progress Work Handed over to KIIFB on 11/08/2021 |
40%
|
27%
|
|||
| 64 | Construction of Olambakkadavu Bridge in Malappuram District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad |
|
Work in progress Work Handed over to KIIFB on 11/08/2021 |
60%
|
17%
|
|||
| 65 | Budget work 2020-21-Construction of Kodumbu Foot bridge across Sokanashini River in Kodumbu Gramapanchayath |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Palakkad |
|
Work in progress Site clearing work completed and compound wall work in progress. |
0%
|
0%
|
|||
| 66 | KIIFB 16-17 Construction of new bridge at Peruman connecting Peruman and Munrothuruth across Ashtamudi Lake. |
Circle:- Bridges South circle Division:- Bridges Division Thiruvananthapuram |
|
Work in progress P2/1, P4/2,P10/4 Boring, P7/3, Liner pitching , Pile Cap bar bendingworks , cage fabrication, Liner fabrication, liner fabrication etc. progressing on site |
16%
|
0%
|
|||
| 67 | Special sanction 2017-18 construction of Enathi Bridge Across karimpuzha river in malappuram district |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad |
|
Work Stopped Piers and hammer heads are completed , 1 deck slab completed. awaiting for approval revised AS to re start the works |
40%
|
21%
|
|||
| 68 | KIIFB Project- Construction of New Rannivaliya Bridge Across Pampa River in Pathanamthitta |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha |
|
Work in progress Agreement to lay underground electric / ducts at ch…… …. Of Thonnakkadu Vazhuvadikkadavu road in front of Perigelippuram temple on this the ----------------- day of Two Thousand Twenty by Executive Engineer, Project Management Harippad Mavelikkara Unit ( here in after referred to as the party) which expression shall included his heirs executors and administrators permitted to assigns on the one part and Executive Engineer Bridges Division Alappuzha in favour of the Governor of Kerala ( here in after referred to as the Government) on the other part.\r\nWhere as the Executive Engineer, KSEB Project Management Harippad Mavelikkara unit has applied for to Department PWD Bridges Division Alappuzha for laying under ground electric cable across the road at ch………………….. of Thonnakkadu – Vazhuvadikkadavu road in front of Peringelippuram temple.\r\nAnd where as the Department have agreed to grand such permission on the terms and conditions here in after mentioned. |
35%
|
0%
|
|||
| 69 | Construction of Chediyalakadavu bridge across mayyazhipuzha on Kunhipuramukku-Mudavantheri-North ummarathoor road in kozhikode district |
Circle:- Bridges North Circle Division:- Bridges Division Kozhikode |
|
Work Stopped Due to Foundation problems on Abutment A2 and Pier P2 Contractor stopped the work.Revised Estimate submitted for approval |
33%
|
0%
|
|||
| 70 | KIIFB 2016-17 Construction of bridge at across Punnamada starting point in Alappuzha District |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha |
|
Technical Sanction Stage File haded over to Executive engineer KRFB PMU Alappuzha on 23-06-2021 |
0%
|
0%
|
|||