| Sl.No | Project Name | Office | Admnistrative Sanction [Order No,Dated,Amt] |
Current Status of Work | Physcical Progress | Financial Progress | |||
|---|---|---|---|---|---|---|---|---|---|
| 41 | Construction of Koottilathara Bridge across Tirur puzha in Tanur LAC in Malappuram District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Manjeri |
|
Technical Sanction Stage TS estimate under preparation. Discussion is going on with land owners for direct purchase of land. |
0%
|
0%
|
|||
| 42 | Construction of Muttikadavu Bridge across Punnappuzha in Nilambur LAC in Malappuram District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Manjeri |
|
Technical Sanction Stage Work under tendering process |
0%
|
0%
|
|||
| 43 | Construction of Kannukadavu Bridge across Poonkudi thodu in Ernad LAC in Malappuram District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Manjeri |
|
Work Tendered Work tendered |
0%
|
0%
|
|||
| 44 | Reconstruction of Maniyanpara Bridge at Tarur Ring Road(Pilappully-Maniyanpara Road) in Tarur LAC,Palakkad District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Palakkad |
|
Work Tendered Work tendered |
0%
|
0%
|
|||
| 45 | GENERAL-Reconstruction of Punnappadam(Mampad) Cuaseway Bridge across Punnappadam river in Alathur LAC in Palakkad District |
Circle:- Bridges North Circle Division:- Bridges Division Palakkad Sub Division:- Bridges Sub Division Palakkad |
|
Work Tendered Work tendered |
0%
|
0%
|
|||
| 46 | KIIFB - 2016-17 Construction of New Kozhenchery bridge across Pampa river in Pathanamthitta District. |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha |
|
Work in progress Week ending 10/07/2021 Activities\r\n04/07/2021 Holiday\r\n05/07/2021 Arch profiling and reinforcement works of P4-P5 span \r\n06/07/2021 Arch profiling and reinforcement works of P4-P5 span \r\n07/07/2021 Arch profiling and reinforcement works of P4-P5 span \r\n08/07/2021 Arch profiling and reinforcement works of P4-P5 span \r\n09/07/2021 Arch profiling and reinforcement works of P4-P5 span \r\n10/07/2021 Arch profiling and reinforcement works of P4-P5 span |
47%
|
0%
|
|||
| 47 | Budget work 2019-20 construction of Upedesikadavu bridge across Pamba River in Pathanamthitta District |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha Sub Division:- Bridges Sub Division Thiruvalla |
|
Work in progress Week ending 10/07/2021 Activities\r\n04/07/2021 Holiday\r\n05/07/2021 Reinforcement works for pile cap, substructure of A1, P1 and P2\r\n(Site flooded)\r\n06/07/2021 Reinforcement works for pile cap, substructure of A1, P1 and P2\r\n(Site flooded)\r\n07/07/2021 Reinforcement works for pile cap, substructure of A1, P1 and P2\r\n(Site flooded)\r\n08/07/2021 Reinforcement works for pile cap, substructure of A1, P1 and P2\r\n(Site flooded)\r\n09/07/2021 Reinforcement works for pile cap, substructure of A1, P1 and P2\r\n(Site flooded)\r\n10/07/2021 Reinforcement works for pile cap, substructure of A1, P1 and P2\r\n(Site flooded) |
25%
|
0%
|
|||
| 48 | KIIFB 2016-17 widening of Savacotta bridge (Powerhouse Bridge)across Vada canal along with an FoB and Reconstruction of Kommady Bridge at Kommady junction inAlappuzha District |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha |
|
Work in progress Savakotta Bridge - Pile - 12/12, Pile cap - 4/4 completed. Box girder –12/13, Foot bridge slab completed. Kommady Bridge- Kommady old Bridge demolished. Temporary island Work in progress. |
35%
|
0%
|
|||
| 49 | KIIFB 2016 17 Construction of Nedumbrakkadu Vilakkumaram Bridge across VayalarKayal in Alappuzha District. |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha |
|
Work in progress Weekly progress report (28/06/2021 to 03/07/2021)\r\nDate Activity\r\n28-06-2021 Rubble shifting and filling for box culvert. \r\n29-06-2021 P2 pier cap de shuttering work. \r\n30-06-2021 P3 pier cap steel alignment work. \r\n01-07-2021 P3 pier cap steel work started. \r\n02-07-2021 Box culvert PCC work.\r\n03-07-2021 Box culvert reinforcement work in progress. |
50%
|
0%
|
|||
| 50 | KIIFB 2016-2017 Construction of Perumbalam Panavally Bridge in Alappuzha District |
Circle:- Bridges South circle Division:- Bridges Division Alappuzha |
|
Work in progress DESCRIPTION- Pile - 15/148 completed |
10%
|
0%
|
|||