Budget work 2015-16 providing BM&BC to mananthavadi pakramthalam road from km 10/240 in wayanad district

   General Details
Roads
Roads Division Wayanad
Roads
R & B North Circle
Roads Division Wayanad
WAYANAD
   Project Details
2015-16
3054-01-001-98-00-01-2-N-V
Plan
Budget Works
RD/2016/325
100,000,000/-
(Ten crore )
GO(Rt)n0:1930/2015/PWD 22-12-2015 100,000,000/-
(Ten crore )
WYD/2017-18 /2016/325 28-04-2017 100,000,000/-
(Ten crore )
   Tender Details
11 00-00-0000 0/-
   Agreement Details
SE(K)211/2017-18 14-11-2017 120,932,483/-
(Twelve crore Nine lakh Thirty Two thousand Four hundred Eighty Three )
24-11-2017 1 Years 24-11-2018 31-03-2020
   Work Progress (Last Updated On :14-09-2020 11:48:23 PM)
Work Completed
100%
WORK COMPLETED
100,000,000/-
(Ten crore )
83%
20,000,000/-
(Two crore )
View Progress Photo Gallery