Construction of academic block II of technical high school Adimaly
| General Details | |||||
|---|---|---|---|---|---|
| Buildings | |||||
| Buildings Division Idukki | |||||
| Buildings | |||||
| Buildings CENTRAL CIRCLE | |||||
| Buildings Division Idukki | |||||
| IDUKKI | |||||
| Project Details | |||||
| 2016-17 | |||||
| NABARD Works | |||||
| RIDF XXII | |||||
| 2016/7946 | |||||
| 43,942,993/- (Four crore Thirty Nine lakh Forty Two thousand Nine hundred Ninety Three )
|
|||||
| GO(RT) 165/2017 | 02-02-2017 | 55,000,000/- (Five crore Fifty lakh )
|
| 5399/2017-18 | 28-03-2018 | 55,000,000/- (Five crore Fifty lakh )
|
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 14/18-19/SE CC/TSR | 10-08-2018 | 38,162,626/- (Three crore Eighty One lakh Sixty Two thousand Six hundred Twenty Six )
|
20-08-2018 | 24 Months | 20-08-2020 | 00-00-0000 |
| Work Progress (Last Updated On :04-05-2021 11:58:21 AM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| 32,822,454/- (Three crore Twenty Eight lakh Twenty Two thousand Four hundred Fifty Four )
86%
|
|||||
| 0/- | |||||
| View Progress Photo Gallery | |||||