Construction of academic block II of technical high school Adimaly

   General Details
Buildings
Buildings Division Idukki
Buildings
Buildings CENTRAL CIRCLE
Buildings Division Idukki
IDUKKI
   Project Details
2016-17
NABARD Works
RIDF XXII
2016/7946
43,942,993/-
(Four crore Thirty Nine lakh Forty Two thousand Nine hundred Ninety Three )
GO(RT) 165/2017 02-02-2017 55,000,000/-
(Five crore Fifty lakh )
5399/2017-18 28-03-2018 55,000,000/-
(Five crore Fifty lakh )
   Agreement Details
14/18-19/SE CC/TSR 10-08-2018 38,162,626/-
(Three crore Eighty One lakh Sixty Two thousand Six hundred Twenty Six )
20-08-2018 24 Months 20-08-2020 00-00-0000
   Work Progress (Last Updated On :04-05-2021 11:58:21 AM)
Work Completed
100%
32,822,454/-
(Three crore Twenty Eight lakh Twenty Two thousand Four hundred Fifty Four )
86%
0/-