Construction of Silver Jubile Memorial Academic Block,Government Polytechnic,Perithalmannna
| General Details | |||||
|---|---|---|---|---|---|
| Buildings | |||||
| Buildings Section,Perinthalmanna | |||||
| Buildings | |||||
| BuildingsNORTH CIRCLE | |||||
| Buildings Division Malappuram | |||||
| BUILDINGS SUB DIVISION PERINTHALMANNA | |||||
| Buildings Section,Perinthalmanna | |||||
| MALAPPURAM | |||||
| Project Details | |||||
| 2015-16 | |||||
| Plan | |||||
| Budget Works | |||||
| BL/2017/4591 | |||||
| 44,484,523/- (Four crore Forty Four lakh Eighty Four thousand Five hundred Twenty Three )
|
|||||
| GO.(Rt)No.1641/2015/H.Edn | 30-06-2015 | 55,000,000/- (Five crore Fifty lakh )
|
| 4411/2017-18 | 14-02-2018 | 55,000,000/- (Five crore Fifty lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 0 | 00-00-0000 | 0/- | Sri. Sushanth E, Oorakam, Melmuri. PO, Malappuram | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| SE(K) 73 /2019-20 | 30-01-2020 | 36,869,720/- (Three crore Sixty Eight lakh Sixty Nine thousand Seven hundred Twenty )
|
24-05-2018 | 18 Months | 24-11-2019 | 00-00-0000 |
| Work Progress (Last Updated On :19-03-2021 0:21:40 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| Work Completed | |||||
| No sketch found | |||||
| 16,721,317/- (One crore Sixty Seven lakh Twenty One thousand Three hundred Seventeen )
45%
|
|||||
| 7,718,599/- (Seventy Seven lakh Eighteen thousand Five hundred Ninety Nine )
|
|||||
| View Progress Photo Gallery | |||||