CRF 2017-18 Re construction of Arikkadavu bridge and approach road in Kanhangad in Kasaragod district.

   General Details
Roads
NH DIVISION KANNUR
NH
NH NORTH CIRCLE
NH DIVISION KANNUR
KANNUR
   Project Details
2017-18
State Plan
CRF Projects
NH/2019/174
120,000,000/-
(Twelve crore )
RW/NH-28014/03/2016-KL/Zone III 28-01-2018 120,000,000/-
(Twelve crore )
NHBSK/2019-20/NH/2019/174 27-04-2019 120,000,000/-
(Twelve crore )
   Tender Details
Bid no 04/2019-20/SE/NH/KKD/SN 27-05-2019 88,311,575/-
(Eight crore Eighty Three lakh Eleven thousand Five hundred Seventy Five )
Sri sreekandan Nair kasaragod
   Agreement Details
24/2019-20/SE/NH/KKD 17-09-2019 88,311,575/-
(Eight crore Eighty Three lakh Eleven thousand Five hundred Seventy Five )
23-09-2019  Months 23-09-2020 00-00-0000
   Work Progress (Last Updated On :24-09-2021 0:54:35 PM)
Work in progress
76%
Bridge proper completed. Immediate approach work ,GSB work, Rivertraining work, retaining wall work and broken parapet at immediate approach work etc.in progress. (76.60% work completed)
No sketch found
63,860,007/-
(Six crore Thirty Eight lakh Sixty thousand Seven )
72%
0/-
View Progress Photo Gallery