CRF 2018-2019 Improvements to choyyankode - Mukkada - Beemanadi road in kasargode district
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| NH DIVISION KANNUR | |||||
| NH | |||||
| NH NORTH CIRCLE | |||||
| NH DIVISION KANNUR | |||||
| KANNUR | |||||
| Project Details | |||||
| 2018-19 | |||||
| State Plan | |||||
| CRF Projects | |||||
| NH/2019/17 | |||||
| 170,000,000/- (Seventeen crore )
|
|||||
| RW/NH/28014/03/2016-KL-ZoneIII | 05-01-2019 | 170,000,000/- (Seventeen crore )
|
| NHBSK/2018-19/NH/2019/17 | 06-02-2019 | 170,000,000/- (Seventeen crore )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 16(rt)/2018-2019 | 12-03-2019 | 159,897,870/- (Fifteen crore Ninety Eight lakh Ninety Seven thousand Eight hundred Seventy )
|
K M Abdulla Kunhi PWD contractor Kasargode | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 04/2019-20/Se/NH/KKD | 17-06-2019 | 159,897,870/- (Fifteen crore Ninety Eight lakh Ninety Seven thousand Eight hundred Seventy )
|
26-06-2019 | 9 Months | 26-03-2020 | 31-12-2020 |
| Work Progress (Last Updated On :16-07-2021 2:14:54 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| Work completed | |||||
| No sketch found | |||||
| 60,868,879/- (Six crore Eight lakh Sixty Eight thousand Eight hundred Seventy Nine )
38%
|
|||||
| 0/- | |||||
| View Progress Photo Gallery | |||||