2016/17 KIIFBIMPROVEMENTS AND PROVIDING BM & BC SURFACING TO KADUNGALLUR VILAYIL CHALIYAPPURAM ROAD Km 0/000 to 8/200 IN KONDOTTY LAC
| General Details | |||||
|---|---|---|---|---|---|
| Roads | |||||
| Kondotti Section | |||||
| Roads | |||||
| R & B North Circle | |||||
| Roads Division Malappuram | |||||
| Roads Sub Division Tirur | |||||
| Kondotti Section | |||||
| MALAPPURAM | |||||
| Project Details | |||||
| 2016-17 | |||||
| KIIFB | |||||
| Other KIIFB Works | |||||
| RD/2016/6501 | |||||
| 162,985,489/- (Sixteen crore Twenty Nine lakh Eighty Five thousand Four hundred Eighty Nine )
|
|||||
| GO (Rt)No.1502/2016/pwd | 01-10-2018 | 100,000,000/- (Ten crore )
|
| MNJ/2018-19/2016/6501 | 26-05-2018 | 164,100,000/- (Sixteen crore Forty One lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 2018-KRFB-206696-1 | 29-05-2018 | 135,214,206/- (Thirteen crore Fifty Two lakh Fourteen thousand Two hundred Six )
|
PMR CONSTRUCTION COMPANY MELMURI PO MALAPPURAM | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 34/PWD004-99/PD/PMU-KRFB/2018-19 | 01-10-2018 | 135,214,206/- (Thirteen crore Fifty Two lakh Fourteen thousand Two hundred Six )
|
09-10-2018 | 1 Years | 09-10-2019 | 08-08-2020 |
| Work Progress (Last Updated On :08-10-2020 4:34:24 PM) | |||||
|---|---|---|---|---|---|
| Work Completed | |||||
|
100%
|
|||||
| work completed | |||||
| No sketch found | |||||
| 103,955,365/- (Ten crore Thirty Nine lakh Fifty Five thousand Three hundred Sixty Five )
77%
|
|||||
| 0/- | |||||
| View Progress Photo Gallery | |||||