GOVT. TDMCH COMPLEX, VANDANAM, ALAPPUZHA- NABARD ASSISTANCE PROJECT RIDF XXII- CONSTRUCTION OF BUILDING FOR OBSTETRICS AND GYNAECOLOGY DEPARTMENT
| General Details | |||||
|---|---|---|---|---|---|
| Buildings | |||||
| Buildings Division Alappuzha | |||||
| Buildings | |||||
| Buildings SOUTH CIRCLE | |||||
| Buildings Division Alappuzha | |||||
| ALAPPUZHA | |||||
| Project Details | |||||
| 2016-17 | |||||
| 4210-03-105-30-00-00-0-P-V | |||||
| NABARD Works | |||||
| RIDF XXII | |||||
| BL/2016/5996 | |||||
| 269,226,039/- (Twenty Six crore Ninety Two lakh Twenty Six thousand Thirty Nine )
|
|||||
| G.O(Rt)No.73/2017/H&FWD | 12-01-2017 | 300,000,000/- (Thirty crore )
|
| 557/2018-2019 | 27-04-2018 | 300,000,000/- (Thirty crore )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| PQ-03/SESCBL/2018-19 | 25-06-2018 | 236,195,442/- (Twenty Three crore Sixty One lakh Ninety Five thousand Four hundred Forty Two )
|
ABDUL VAHID J,E.J.CONSTRUCTIONS,KURUDANTAYYATH,KADATHOOR.P.O,KARUNAGAPPALLY | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 46/SEBSC/2018-19 | 01-11-2018 | 236,195,442/- (Twenty Three crore Sixty One lakh Ninety Five thousand Four hundred Forty Two )
|
04-09-2018 | 30 Months | 04-03-2021 | 00-00-0000 |
| Work Progress (Last Updated On :28-12-2020 10:28:59 AM) | |||||
|---|---|---|---|---|---|
| Work in progress | |||||
|
63%
|
|||||
| 5th floor(TERRACE FLOOR) shuttering work 90% Finished,steel work for beam 90% completed,steel work for slab 50% completed | |||||
| 80,000,000/- (Eight crore )
34%
|
|||||
| 0/- | |||||