H&FWD NABARD RIDF XX Construction of a Building for Community Health Centre Paika

   General Details
Buildings
Buildings Section, Kanjirappally
Buildings
Buildings SOUTH CIRCLE
Buildings Division Kottayam
BUILDINGS SUB DIVISION KANJIRAPPALLY
Buildings Section, Kanjirappally
KOTTAYAM
   Project Details
2014-15
4210-01-110-75-01-00-00-P-V
NABARD Works
RIDF XX
EST NO.2016/1309
166,981,501/-
(Sixteen crore Sixty Nine lakh Eighty One thousand Five hundred One )
G.O.(Rt)No.936/2015/H&FWD 21-03-2015 19,936,000/-
(One crore Ninety Nine lakh Thirty Six thousand )
Order No.3901/2015-2016 03-03-2016 199,360,000/-
(Nineteen crore Ninety Three lakh Sixty thousand )
   Tender Details
PQ-01/SESCBL/2016-2017 25-06-2016 146,719,930/-
(Fourteen crore Sixty Seven lakh Nineteen thousand Nine hundred Thirty )
M/S Creators constructions Kureakal Building Edappally Toll Kochi
   Agreement Details
52/SEBSC/2016-2017 25-06-2016 146,719,930/-
(Fourteen crore Sixty Seven lakh Nineteen thousand Nine hundred Thirty )
20-10-2017  Months 19-10-2019 30-11-2020
   Work Progress (Last Updated On :17-04-2021 0:53:08 PM)
Work in progress
99%
Proposed Building work almost completed.
66,486,999/-
(Six crore Sixty Four lakh Eighty Six thousand Nine hundred Ninety Nine )
45%
24,753,305/-
(Two crore Forty Seven lakh Fifty Three thousand Three hundred Five )
View Progress Photo Gallery