NABARD RIDF XXII(2016-17)- Infrastructure works for Additional Hospital Building in Taluk Hospital, Vythiri
| General Details | |||||
|---|---|---|---|---|---|
| Buildings | |||||
| Buildings Division Wayanad | |||||
| Buildings | |||||
| BuildingsNORTH CIRCLE | |||||
| Buildings Division Wayanad | |||||
| WAYANAD | |||||
| Project Details | |||||
| 2016-17 | |||||
| 4210-01-110-75-00-00-0-P-V | |||||
| NABARD Works | |||||
| RIDF XXII | |||||
| BL/2015/4702 | |||||
| 75,000,000/- (Seven crore Fifty lakh )
|
|||||
| GO(RT) NO 73/2017/H&FWD dated 12/01/17 | 12-01-2017 | 75,000,000/- (Seven crore Fifty lakh )
|
| REG NO: 3946/2017-18 ORDER NO 2017-18 2015/4702 | 19-01-2018 | 75,000,000/- (Seven crore Fifty lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| 45/2017-18/SENC/45 | 17-01-2018 | 42,982,521/- (Four crore Twenty Nine lakh Eighty Two thousand Five hundred Twenty One )
|
M.G JAIJITH ,KARTHIKA ,MANICHIRA, SULTAN BATHERY | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| SE(K)25/2018-19 | 27-06-2018 | 42,982,521/- (Four crore Twenty Nine lakh Eighty Two thousand Five hundred Twenty One )
|
14-11-2018 | 2 Years | 14-11-2020 | 00-00-0000 |
| Work Progress (Last Updated On :28-01-2021 2:27:41 PM) | |||||
|---|---|---|---|---|---|
| Work Awarded | |||||
|
58%
|
|||||
| Second floor slab concrete completed and Headroom,machine room steel work in progress. Masonry work in progress | |||||
| 14,707,373/- (One crore Forty Seven lakh Seven thousand Three hundred Seventy Three )
34%
|
|||||
| 3,717,645/- (Thirty Seven lakh Seventeen thousand Six hundred Forty Five )
|
|||||
| View Progress Photo Gallery | |||||