NABARD assistance under RIDF XXII Gl -Edn. VHSE - Construction of building for GVHSS Wandoor
| General Details | |||||
|---|---|---|---|---|---|
| Buildings | |||||
| Buildings Division Malappuram | |||||
| Buildings | |||||
| BuildingsNORTH CIRCLE | |||||
| Buildings Division Malappuram | |||||
| MALAPPURAM | |||||
| Project Details | |||||
| 2016-17 | |||||
| 4202-01-202-86-00-00-0-P-V | |||||
| NABARD Works | |||||
| RIDF XXII | |||||
| BL/2018/7815 | |||||
| 12,192,143/- (One crore Twenty One lakh Ninety Two thousand One hundred Forty Three )
|
|||||
| G.O. (Rt) No.4041/2016/Gl Edn | 24-11-2016 | 12,500,000/- (One crore Twenty Five lakh )
|
| 4213/2018-2019 | 22-12-2018 | 12,365,000/- (One crore Twenty Three lakh Sixty Five thousand )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| DB5-TN/54/2018-19 | 26-12-2018 | 12,192,143/- (One crore Twenty One lakh Ninety Two thousand One hundred Forty Three )
|
Sri Mujeebu Rahman. N.K Panthakalakath H Areacode PO | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| SE(K) 03/2019-20 | 30-05-2019 | 10,134,555/- (One crore One lakh Thirty Four thousand Five hundred Fifty Five )
|
10-06-2019 | Months | 09-04-2020 | 00-00-0000 |
| Work Progress (Last Updated On :15-04-2021 3:06:35 PM) | |||||
|---|---|---|---|---|---|
| Work in progress | |||||
|
49%
|
|||||
| GF Slab shuttering work progressing. | |||||
| 531,384/- (Five lakh Thirty One thousand Three hundred Eighty Four )
5%
|
|||||
| 0/- | |||||
| View Progress Photo Gallery | |||||