Works of Rs.1 Crore and above
| Sl.No | Project Name | Office | Admnistrative Sanction [Order No,Dated,Amt] |
Current Status of Work | Physcical Progress | Financial Progress |
|---|---|---|---|---|---|---|
| 11 | NABARD RIDF XXII(2016-17)- Infrastructure works for Additional Hospital Building in Taluk Hospital, Vythiri |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Wayanad |
GO(RT) NO 73/2017/H&FWD dated 12/01/17 12-01-2017 75,000,000/- |
Work Awarded Second floor slab concrete completed and Headroom,machine room steel work in progress. Masonry work in progress |
58%
|
34%
|
| 12 | NABARD RIDF XXII(2016-17) - Infrastructure works for additional Hospital Building in Taluk Hospital, Sulthan Bathery, Wayanad District. |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Wayanad Sub Division:- BUILDINGS SUB DIVISION KALPETTA Section:- Buildings Section-II, Kalpatta |
G.O(Rt)No:73/2017 H&FWD 12-01-2017 250,000,000/- |
Work in progress Plastering work in progress |
70%
|
41%
|
| 13 | Higher Education-Technical-NABARD-RIDF-XXII-Additional infrastructure work for GPC,Adoor(Construction of Mechanical laboratory Building) |
Circle:- Buildings SOUTH CIRCLE Division:- Buildings Division Pathanamthitta |
127/2017/HEdn 24-01-2017 16,500,000/- |
Work in progress Plastering works in progress |
67%
|
0%
|
| 14 | NABARD- RIDF-TRANCHE-XXII-(2016-2017)-INFRASTRUCTURE WORKS IN HOSPITAL FOR LEPROSY SANATORIUM, NOORANADU, ALAPPUZHA-CONSTRUCTION OF MALE AND FEMALE WARD AT LS, NOORANAD |
Circle:- Buildings SOUTH CIRCLE Division:- Buildings Division Alappuzha Sub Division:- BUILDINGS SUB DIVISION HARIPPAD Section:- Buildings Section, Mavelikkara |
GO(Rt)No.196/2017/H&FWD 27-01-2017 403,000,000/- |
Work in progress Total 7 block Ground floor roof completed, Brik work and plastering is progressed |
60%
|
16%
|
| 15 | NABARD RIDF XXII- Additional infrastructure works in Central Hatchery at Puliyoor Panchayath Chengannur, Alappuzha- Construction of staff and labour quarters two tier parent stock building and labour retiring room at Puliyoor village campus of Central Hatchery Chengannur |
Circle:- Buildings SOUTH CIRCLE Division:- Buildings Division Alappuzha Sub Division:- BUILDINGS SUB DIVISION CHENGANOOR Section:- Buildings Section, Chengannur |
GO (MS) No. 7/2017AHD 09-03-2017 56,050,000/- |
Work in progress Two buildings finishing work Two quarters FF slab reinforcement work completed |
85%
|
0%
|
| 16 | NABARD - RIDF XXIII- General Education Department - Higher Secondary Education- Construction of Additional infrastructure works for Govt.Girls Higher Secondary School , Parayanchery , Feroke in Public Works Department Kozhikode District |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kozhikkode Sub Division:- BUILDINGS SUB DIVISION KOZHIKKODE |
GO(Rt)No.4696/201/Gl.Edn 17-12-2017 23,739,000/- |
Work in progress First Floor slab reinforcement work in progress. |
30%
|
0%
|
| 17 | H & FWD-NABARD -RIDF(Tranche XXIV) 2018-19 Construction of Trauma care and surgery ward for govt taluk hospital, chalakkudy |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Thrissur |
GO(Rt)No.3345/2018/H& FWD 08-11-2018 53,500,000/- |
Work in progress FF slab concreting of half portion completed.Balance half portion pedestal concreting, plinth protection solid block masonry & earthfilling completed. Plinth beam reinforcement work in progress |
13%
|
0%
|
| 18 | NABARD-RIDF XXIV-Construction of Taluk Hospital koothuparamba,Kannur (first phase) |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kannur Sub Division:- BUILDINGS SUB DIVISION THALASSERY Section:- Buildings Section, Thalasserry |
GO(Rt)3345/2015/H&FWD TVM 08-11-2018 130,453,000/- |
Work in progress Pile cap work & STP tank work in progress |
15%
|
0%
|
| 19 | NABARD XXIV-Construction of Building for Iriveri CHC, Chakkarakal |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kannur Sub Division:- BUILDINGS SUB DIVISION KANNUR Section:- Special Buildings Section, Kannur |
GO(Rt) No 3345/2018/ H&FWD 08-11-2018 109,000,000/- |
Work in progress Tentative design received |
0%
|
0%
|
| 20 | Construction of CHC building,Erumapetty,Kunnamkulam |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Thrissur |
GO(Rt)No.224/2019/H& FWD 30-01-2019 72,000,000/- |
Work in progress Approved draft plan obtained from superintendent of CHC has to be submitted to Architectural wing |
0%
|
0%
|