Works of Rs.1 Crore and above
| Sl.No | Project Name | Office | Admnistrative Sanction [Order No,Dated,Amt] |
Current Status of Work | Physcical Progress | Financial Progress |
|---|---|---|---|---|---|---|
| 71 | Construction of Head Quarters building for Food Safety Commissionerate, Thiruvananthapuram |
Circle:- Buildings SOUTH CIRCLE Division:- Buildings Division Thiruvananthapuram |
Go(Rt)No-3405/2016/H&FWD & Go(Rt)No-1762/2 24-06-2017 25,500,000/- |
Work in progress work in progress |
25%
|
44%
|
| 72 | Construction of Excise Circle Office building at Wadakkanchery |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Thrissur |
GO(Rt)No. 559/2017/TD dt. 11.07.2017 FOR 100L 11-07-2017 10,000,000/- |
Work in progress flooring progress |
96%
|
0%
|
| 73 | CONSTRUCTION OF A BUILDING FOR NEW ACADEMIC BLOCK AT GPTC, CHELAD, KOTHAMANGALAM |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Ernakulam Sub Division:- BUILDINGS SUB DIVISION PERUMBAVOOR Section:- Buildings Section, Kothamangalam |
GO(Rt)No.1349/2017H.Edn 18-07-2017 50,000,000/- |
Work in progress First floor column work in progress |
27%
|
0%
|
| 74 | CONSTRUCTION OF WORKSHOP LABORATORY AT GOVT.POLYTECHNIC COLLEGE MALAPARAMBA KOZHIKODE |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kozhikkode Sub Division:- BUILDINGS SUB DIVISION KOZHIKKODE |
1349/2017 HEDN 18-07-2017 49,200,000/- |
Work in progress TEST PILE INSTALLED |
5%
|
0%
|
| 75 | Central prison Viyyur Construction of Multipurpose Auditorium |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Thrissur |
G.O.(MS) No 156/2017/Home dtd Tvm 19/7/2017 for 16 19-07-2017 16,200,000/- |
Work in progress almost completed |
98%
|
13%
|
| 76 | Prisons Annual Plan Scheme- Modernization of prisons 2017-2018 -District Jail Mananthavady-Construction of superintendent quarters, Staff quarters and rest room for staff |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Wayanad Sub Division:- Buildings Sub Division Mananthavady |
GO(MS) No. 156/2017/Home 19-07-2017 20,000,000/- |
Work in progress Staff qtrs superindent qtrs work completed.soil removed by DTPC and retaining wall work in progress . |
98%
|
0%
|
| 77 | Construction of Barrack for Open Prison , Cheemeni |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kasaragod Sub Division:- BUILDINGS SUB DIVISION KANJANGAD |
Go(ms)No.156/2017/Home 19-07-2017 30,800,000/- |
Work in progress F.F slab Centering and shuttering work progressing |
40%
|
40%
|
| 78 | Construction of a new building for Excise office and Excise circle office,Adoor |
Circle:- Buildings SOUTH CIRCLE Division:- Buildings Division Pathanamthitta |
GO(Rt) No.635/2017/LAW department 30-07-2017 28,000,000/- |
Work in progress nearing completion |
99%
|
14%
|
| 79 | Construction of new Building for Taluk Hospital Varkala Phase II |
Circle:- Buildings SOUTH CIRCLE Division:- Special Buildings Division Thiruvananthapuram |
GO(Rt) No.643/2017/H& FWD 13-08-2017 70,500,000/- |
Work in progress Solid block and plastering works in progress |
30%
|
10%
|
| 80 | Construction of addtional judicial complex Kattappana Idukki phase 1-Balance work |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Idukki |
GO(rt) no -2283/2017 23-08-2017 35,000,000/- |
Work in progress Foundation works under progress |
20%
|
0%
|