| 61 | Construction of Vocational Higher secondary school at Kumily |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Idukki |
762/2017 20-03-2017 14,700,000/- |
Work in progress Plastering nearing completion.Plumbing work in progress |
78%
|
0%
|
| 62 | Construction of New Building for Samrudhi Kendram, Arattupuzha |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Thrissur Sub Division:- BUILDINGS SUB DIVISION THRISSUR Section:- Buildings Section Thrissur |
GO(Rt) No:826/2017/S ST Dptmt dt 25.03.2017 FOR 35 25-03-2017 35,000,000/- |
Work Started waiting for building permitt from vallachira grama panchayath |
5%
|
0%
|
| 63 | Construction PWD Rest House at Karumady,in Ambalappuzha Constituency |
Circle:- Buildings SOUTH CIRCLE Division:- Buildings Division Alappuzha |
GO (Rt) No 420/2017/PWD 30-03-2017 33,000,000/- |
Work in progress plastering work on progress |
78%
|
35%
|
| 64 | Construction of an Academic block for Government Technical school Nedumangadu Thiruvananthapurram |
Circle:- Buildings SOUTH CIRCLE Division:- Special Buildings Division Thiruvananthapuram |
GO(Rt) No. 757/2017/HEDN 09-05-2017 60,000,000/- |
Work in progress First floor slab of cellar portion Completed. Half portion of first floor slab concrete works completed. Second floor shuttering works progressing in half portion |
27%
|
0%
|
| 65 | Higher Education Department Collegiate Education Annual Plan 2017 18 Construction of AcademicBlock in SARBTM Govt College Koyilandy Construction of Mens Hostel |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kozhikkode Sub Division:- BUILDINGS SUB DIVISION KOYILANDI |
GO(Rt) No.910/2017/H.Edn 19-05-2017 111,597,000/- |
Work in progress Laterite masonry work in progress |
65%
|
0%
|
| 66 | Higher Education Department Annual Plan 2017 18 Construction of Academic Block for SARBTM Govt College Koyilandy in Kozhikode District |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Kozhikkode Sub Division:- BUILDINGS SUB DIVISION KOYILANDI |
GO(Rt) No.910/2017/H.Edn. 19-05-2017 79,999,998/- |
Work in progress Retaining wall concrete work in progress. |
20%
|
0%
|
| 67 | Construction of a new building for library cum instrumentation block in university college trivandrum |
Circle:- Buildings SOUTH CIRCLE Division:- Special Buildings Division Thiruvananthapuram |
GO (Rt) no 910/2017/HEdn 19-05-2017 93,500,000/- |
Work in progress Second Floor shuttering work in progress |
16%
|
0%
|
| 68 | PWD - AYUSH-HOMEO MEDICAL EDUCATION -PHASE I Construction of building for pharmacy college at iranimuttom |
Circle:- Buildings SOUTH CIRCLE Division:- Special Buildings Division Thiruvananthapuram |
215/2017/AYUSH 26-05-2017 79,700,000/- |
Work in progress Nearly Completion |
99%
|
54%
|
| 69 | HEDN-Technical-Construction of Electrical Engineering Block in Govt.Engineering college ,Sreekrishnapuram |
Circle:- BuildingsNORTH CIRCLE Division:- Buildings Division Palakkad Sub Division:- BUILDINGS SUB DIVISION SHORNUR Section:- Buildings Section, Shornur |
Go(Rt) No 1182/2017/Hedn, TVM 22-06-2017 85,705,348/- |
Work in progress BASEMENT FLOOR ,GROUND FLOOR.FIRST FLOOR COMPLETED.SECOND FLOOR 2/3 rd COMPLETED .REMAINING PORTION CONGRETING PROGRESS .SOLID BLOCK WORK AND PLASTERING PROGRESS. |
52%
|
0%
|
| 70 | Construction of Annex block for Computer Engineering Dept in Govt .Engineering College,Thrissur |
Circle:- Buildings CENTRAL CIRCLE Division:- Buildings Division Thrissur |
GO (Rt) no 1192/2017/H Edn 23-06-2017 25,000,000/- |
Work in progress Finishing work is in progress |
95%
|
46%
|