Construction of parallel bridge to Kodimatha bridge across Kodoor river at Kodimatha in Kottayam district
| General Details | |||||
|---|---|---|---|---|---|
| Bridges | |||||
| Bridges Division Kottayam | |||||
| Bridges | |||||
| Bridges South circle | |||||
| Bridges Division Kottayam | |||||
| KOTTAYAM | |||||
| Project Details | |||||
| 2013-14 | |||||
| 5054-04-101-99-00-16-0-P-V | |||||
| Plan | |||||
| Budget Works | |||||
| NIL | |||||
| 99,900,000/- (Nine crore Ninety Nine lakh )
|
|||||
| GO(RT) No. 682/2013/pwd | 03-05-2013 | 99,900,000/- (Nine crore Ninety Nine lakh )
|
| 13/CEC/2013-14 | 24-01-2014 | 99,900,000/- (Nine crore Ninety Nine lakh )
|
| Tender Details | |||||
|---|---|---|---|---|---|
| PQ20/SESC/2013-14 | 14-02-2014 | 95,106,146/- (Nine crore Fifty One lakh Six thousand One hundred Forty Six )
|
Mathew Korah,Parakudiyil, Nellada P.O, Muvattupuzha | ||
| Agreement Details | ||||||
|---|---|---|---|---|---|---|
| 104/SESC/14-15 | 26-12-2014 | 96,465,356/- (Nine crore Sixty Four lakh Sixty Five thousand Three hundred Fifty Six )
|
01-01-2015 | 18 Months | 01-07-2016 | 00-00-0000 |
| Work Progress (Last Updated On :21-10-2020 0:29:50 PM) | |||||
|---|---|---|---|---|---|
| Work Stopped | |||||
|
60%
|
|||||
| 2 span completed, balance 1 span work pending due to non availability of land. Retaining wall completed at Ettumanoor side. Rehabiltation required for two familes by the Revenue department, which is in progress. | |||||
| 0/-
0%
|
|||||
| 0/- | |||||